Public Tender Standstill & Minimum Submission Period Calculator

Calculate mandatory public procurement standstill periods and earliest lawful contract signature dates under EU Dir. 2014/24/EU (10/15 days), UK PA2023 (8 working days), Germany § 134 GWB, France Art. R.2182-1, and Spain LCSP Art. 153.3.

Standstill duration10 calendar days
Standstill ends (end of day)2026-12-11
Earliest lawful contract signature2026-12-14
Legal basisDir. 2007/66/EC Art. 2a(2); Dir. 2014/24/EU Art. 27–29

Minimum 10 calendar days from the day following electronic dispatch (15 calendar days by non-electronic means). Member States may set longer periods.

Verify national and regional public holidays and the exact tender documents before relying on a legal deadline.

Standstill & Minimum Tender Submission Periods by Jurisdiction

Jurisdiction / Legal regimeStandstill durationMin. Open ProcedureMin. Restricted
European Union — Directive 2014/24/EU (Art. 2a Remedies Dir.)
Dir. 2007/66/EC Art. 2a(2); Dir. 2014/24/EU Art. 27–29
10 / 15 calendar days35 (30 electronic / 15 PIN or urgency)30 request + 30 tender (25 electronic)
United Kingdom — Procurement Act 2023 (s. 51)
UK Procurement Act 2023 s. 51 & s. 54 (UK6 Contract Award Notice)
8 working days (excl. weekends)25 electronic (10 urgency / qualifying planned notice)25 request + 25 tender (electronic)
Germany — § 134 GWB (Vorabinformation / Stillhaltefrist)
§ 134 Abs. 2 GWB; §§ 15–17 VgV
10 / 15 calendar days35 (§ 15 VgV · 30 electronic / 15 urgency)30 request + 30 tender (§ 16 VgV)
France — Code de la commande publique (Art. R.2182-1)
CCP Art. R.2182-1 (Délai de suspension — procédures formalisées)
11 / 16 calendar days35 (30 electronic · Art. R.2161-2 CCP)30 candidacy + 30 tender (25 electronic)
Spain — LCSP 9/2017 (Art. 153.3 · Recurso especial)
Ley 9/2017 (LCSP) Art. 44 & Art. 153.3 (15 días hábiles)
15 working days (excl. weekends)35 SARA (30 electronic · Art. 156 LCSP)30 request + 30 tender (SARA)

Frequently asked questions

How long is the standstill period under UK Procurement Act 2023?

Section 51 of the UK Procurement Act 2023 sets a mandatory standstill period of 8 working days beginning on the day the Contract Award Notice (UK6) is published on Find a Tender (replacing the old 10 calendar days under PCR 2015).

Why does France use 11 calendar days instead of 10?

EU Directive 2007/66/EC sets a floor of at least 10 calendar days for electronic dispatch. France transposed this in Code de la commande publique Art. R.2182-1 as 11 calendar days (electronic) and 16 calendar days (other means) for formal procedures.

Does this calculator account for regional public holidays?

It automatically excludes Saturdays and Sundays for working-day regimes and weekend-ending EU calendar rules, but national and regional bank holidays vary by jurisdiction — always verify exact dates against the official award notification and local calendar.