Dungeness Site boiler & ancillary equipment removal

Key facts

StatusAwarded
Estimated value£147,000,000
Submission deadlineDeadline not published
PublishedNov 9, 2026
BuyerNuclear Restoration Services Limited
CountryUnited Kingdom · Warrington
CPV code45111000, 42410000, 42416130, 42418000, 45111100, 45111300, 45222110, 45113000, 90650000, 79723000, 71312000, 45262650, 71313400, 42414100
SourceFind a Tender ↗
Open official notice
Status
Awarded
Estimated value
£147,000,000
Submission deadline
Deadline not published
Published
Nov 9, 2026
Buyer
Nuclear Restoration Services Limited
Country
United Kingdom
CPV code
45111000, 42410000, 42416130, 42418000, 45111100, 45111300, 45222110, 45113000, 90650000, 79723000, 71312000, 45262650, 71313400, 42414100
Source
Find a Tender

Contract outcome & evergreen alternatives

This notice is no longer open for submissions. The original remains available for reference.

Awarded supplier / winnerRegistration / LEI numberCountryAwarded contract amountAward date
Aureos Highways Limited
2nd Floor 1 Lindsey Street, London, EC1A 9HP
GB-COH: 14882566United Kingdom£147,000,000Oct 23, 2026

Open tenders in this CPV category (CPV 45000000 · View CPV × country award matrix)

Checked:

The original notice takes precedence. Its status and conditions can change after collection.

Description

Removal of eight boilers and ancillary equipment, including demolition of buildings and safe removal of hazards such as asbestos containing materials. See full description and Scope document for full details.

Lots

  1. 1

    Dungeness ‘A’ is a redundant nuclear power station located on the Romney Marsh in Kent. The power station ceased generation in 2006 and is currently undergoing decommissioning. The scope of works is for the Contractor to undertake the role of “Principal Contractor” for the safe removal of all hazards including Asbestos Containing Materials (ACM’s), soft stripping internal fixtures, fittings & linings and removal of the Boilers, by pass ducts, main gas duct sections, suitable laydown and weatherproof storage. The safe demolition of the buildings adjoining the east and west faces of the reactor buildings of the Dungeness A Site, noting the Blower Halls and Central Control Block are reduced to slab level with other buildings reduced as stated in the scope of works and in accordance with BS6187:2011 Code of Practice for Full and Partial Demolition (Ref. 16.4.1). To provide some idea of scale, Dungeness has eight boilers which will require removal and laydown. These are estimated at 7m in diameter and 21m long, they weigh approximately 700 tonnes each. Approximately 30% of the building structures currently on Site will be removed by the contract. The Employer will apply for any necessary planning permissions and carry out any activities necessary to obtain the Planning Approval. The Contractor is to provide all management, documentation, labour, plant, equipment, and materials to remove the hazards, de-plant all equipment, lifting and removal of the Boilers, by pass ducts, main gas duct sections, suitable laydown and weatherproof storage, demolition of the buildings and make good weatherproof of remaining structures including site remediation. The scope of this project includes the preparation and execution of all necessary investigation work such as ground, geological, ordnance, camera, flow surveys, etc. necessary to complete the scope of works.

Public business contacts

Aimee Ofsarnie

aimee.ofsarnie@nrservices.uk

www.gov.uk

Checked: