SprosRadar
Find tenders
UK Contracts Finder · b757684a-1e7c-4d09-9389-1b91fb4c14f5-921130

Coalsnaughton Support Technical Review

Key facts

StatusAwarded
Estimated value£299,900
Submission deadlineOct 30, 2026, 12:00 PM UTC
PublishedNov 10, 2026
BuyerMINING REMEDIATION AUTHORITY
CountryUnited Kingdom · MANSFIELD
CPV code71530000
SourceUK Contracts Finder ↗
Open official notice

Buyer competition & track record

View buyer →
Collected notices70 open
Confirmed contracts7Top winners by contract awards: BALFOUR BEATTY CIVILS LIMITED

Contract outcome & evergreen alternatives

This notice is no longer open for submissions. The original remains available for reference.

Awarded supplier / winnerRegistration / LEI numberCountryAwarded contract amountAward date
Slr Consulting Ltd
Brockhill Court, B97 6RB
GB-COH: 03880506United Kingdom£299,900Oct 30, 2026

Open tenders in this CPV category (CPV 71000000 · View CPV × country award matrix)

Check eligibility, thresholds & deadlines

Checked:

The original notice takes precedence. Its status and conditions can change after collection.

Description

This notice is intended to inform that a call off from a Framework has taken place.

The Coalsnaughton Incident requires multidisciplinary engineering input across structural, geotechnical, mining and geological matters. WSP is undertaking significant elements of the technical work and engineering development for Phase 2 under separate commissions approved through the MRA Engineering Services Framework.

It is considered appropriate for the MRA to obtain independent technical assurance of key elements of this work. The appointment of SLR provides additional specialist challenge and advice to support the MRA in understanding the technical evidence presented, identifying material gaps or concerns and making informed decisions as the project progresses.

The scope includes:

• review of structural inspection reports relating to properties identified for demolition;
• technical review of proposed protection and demolition works;
• review and interpretation of available site characterisation information;
• engagement with BGS;
• review of relevant WSP technical information and deliverables;
• participation in technical and project meetings; and
• ongoing multidisciplinary technical advice.

The commission is deliberately structured as an assurance and advisory role. SLR will not replace the responsibilities of WSP or other designers and consultants, nor will they make decisions on behalf of the MRA.

Public business contacts

Roger Martin

roger.martin@miningremediation.gov.uk

01623637400

Checked: