SprosRadar
Trouver des marchés
Find a Tender · 108639-2026

Ionad Eilean nan Òige - Phase 3

Faits clés (Key Facts)

StatutOuvert
Montant estimé3 000 000 £GB
Date limite16 déc. 2026, 12:00 UTC
Publié16 nov. 2026
AcheteurComann Eachdraidh Eirisgeidh
PaysRoyaume-Uni · Outer Hebrides
Code CPV45000000
SourceFind a Tender ↗
Ouvrir l’avis officiel
Statut
Ouvert
Montant estimé
3 000 000 £GB
Date limite
16 déc. 2026, 12:00 UTC
Publié
16 nov. 2026
Acheteur
Comann Eachdraidh Eirisgeidh
Pays
Royaume-Uni
Code CPV
45000000
Source
Find a Tender

Vérifié:

L’avis officiel fait foi. Son statut et ses conditions peuvent évoluer après la collecte.

Description

This document contains the Stage 1 Tender for the Community Hub project Ionad Eilean
Na Òige.
1.2 Tender design information is currently being prepared by the appointed design team and is
expected to be completed by early 2027. Comann Eachdraidh Eirisgeidh are looking to
appoint a suitably qualified and experienced contractor on a first stage tender who will
then work with the team to finalise the price, scope of works and programme before being
appointed to carry out the works.
1.3 The first stage will comprise finalising design, programme, cost and contract conditions.
The appointed contractor will require to work collaboratively with the team during this
stage to ensure value for money is achieved.
1.4 The target for entering into contract is end of March 2027 with a site start shortly
thereafter.
Refer to documentation provided for full details.

Lots

  1. 1

    Tender design information is currently being prepared by the appointed design team and is
    expected to be completed by early 2027. Comann Eachdraidh Eirisgeidh are looking to
    appoint a suitably qualified and experienced contractor on a first stage tender who will
    then work with the team to finalise the price, scope of works and programme before being
    appointed to carry out the works.
    1.3 The first stage will comprise finalising design, programme, cost and contract conditions.
    The appointed contractor will require to work collaboratively with the team during this
    stage to ensure value for money is achieved.
    1.4 The target for entering into contract is end of March 2027 with a site start shortly
    thereafter.

    3 000 000 £GB

Coordonnées professionnelles publiques

Sandra MacInnes

sandra@eriskayheritage.scot

+44 1878720713

Vérifié: