Coal Mining Risk Assessment
Auftraggeber: SEVERN TRENT WATER LIMITED
Wert nicht veröffentlicht
Offen
Angebotsfrist: 23. Dez. 2026, 12:00 UTC
| Status | Offen |
|---|---|
| Geschätzter Wert | Wert nicht veröffentlicht |
| Angebotsfrist | 18. Jan. 2027, 23:59 UTC |
| Veröffentlicht | 23. Nov. 2026 |
| Auftraggeber | SEVERN TRENT WATER LIMITED |
| Land | Vereinigtes Königreich · Coventry |
| CPV-Code | 31100000, 42123000, 45232421, 50532000, 50800000 |
| Quelle | Find a Tender ↗ |
Geprüft:
Die amtliche Bekanntmachung ist maßgeblich. Status und Bedingungen können sich nach der Erfassung ändern.
The framework is divided into two lots: Lot 1 - Blower and Compressor Servicing and Maintenance and Lot 2 - Aeration Systems Performance Evaluation and Improvement. Suppliers will be required to deliver services that improve asset reliability, operational performance, energy efficiency, and whole-life value across activated sludge process (ASP) systems.
Lot 1 covers the planned preventative maintenance, condition monitoring, repair, overhaul, breakdown response, and lifecycle management of air blowers, air compressors, gas blowers, and gas compressors, including associated control and instrumentation equipment.
Lot 2 focuses on identifying and delivering energy and process efficiency improvements through blower performance testing, aeration system assessments, ASP process optimisation, diffuser performance evaluation and acid cleaning, whole-life cost analysis, and support for capital improvement projects. Suppliers may also be required to provide independent technical advice, project management, and Principal Contractor or Principal Designer services under CDM 2015.
The framework aims to support reduced energy consumption, improved process performance, enhanced asset lifespan, and continuous improvement across the Utilities' wastewater treatment operations. Suppliers will be expected to operate to defined performance standards, provide regular management information, and proactively identify innovation and efficiency opportunities throughout the contract term